Permitting Procedures
Ready to Build Your Dream in Sampson County? A Permitting Guide
Building your dream home or starting a renovation project in Sampson County is an exciting time! To ensure a smooth process, obtaining the necessary permits is crucial. This guide will walk you through the steps involved.
1. Zoning Approval:
The first step is to secure zoning approval for your project location. This verifies that your plans comply with zoning regulations in your area. Here's a breakdown of who to contact:
- Incorporated Towns: Residents of City of Clinton, Autryville, Faison, Garland, Harrells, Newton Grove, Roseboro, Salemburg, and Turkey should contact their respective town's zoning department using the phone numbers listed below:
- Autryville: 910-525-4567
- Faison: 910-267-2721
- Garland: 910-529-4141
- Harrells: 910-532-4040
- Newton Grove: 910-594-0827
- Roseboro: 910-525-4121
- Salemburg: 910-525-5650
- Turkey: 910-592-7273
- City of Clinton: 910-299-4094
- Unincorporated Areas: If you reside outside these towns and their ETJ, contact the Sampson County Planning & Zoning Department at (910) 631-1039.
2. Floodplain Considerations:
If your property falls within a designated floodplain, you'll need to provide an Elevation Certificate to the Inspections Office before receiving final approval.
3. Septic Tank Permit:
Obtaining a septic tank permit from the Sampson County Health Department's Environmental Health Section is crucial. Here's what you'll need:
- A completed and signed application for an improvement permit (with the corresponding fee).
- A plot map of your lot, including dimensions, dwelling location with setbacks, driveway details, preferred septic tank/well locations, and any existing septic systems or wells.
An Environmental Health Officer will inspect your site. If approved, you'll receive an improvement permit specifying the septic tank system size, location, and any required modifications.
4. Building Permits:
Finally, you'll need a building permit from the Inspections Office for new construction projects. To apply, you'll need to submit:
- Two sets of scaled plans (one set for residential projects) detailing:
- Foundation
- Floor plan
- Wall details
- All four elevations (front, back, and sides)
- A copy of your valid septic tank permit
- A copy of your valid zoning approval
Additional Notes:
- Subcontractors (electrical, plumbing, mechanical, etc.) need to obtain their own permits based on the project's specifics.
- Permit fees vary depending on the total square footage (heated and unheated) of your project.
By following these steps and acquiring the necessary permits, you can ensure a smooth and compliant building experience in Sampson County. If you have any questions or require further clarification, don't hesitate to contact the relevant department!